Question: 3. Applications are scanned in a process with two resources. The first resource has a capacity of 0.74 applications per minute. The capacity of

3. Applications are scanned in a process with two resources. The first

3. Applications are scanned in a process with two resources. The first resource has a capacity of 0.74 applications per minute. The capacity of the second resource is 1.5 applications per minute. The first resource has 9 workers and the second resource has 1 worker. What is the capacity of the process if workers can now work at both resources and processing times do not change? (10 points) Note: Do not round intermediate calculations. Round your answer to 3 decimal places.