Question: 5. Project Network Design (5 pts.) (Follow Topic: Project Network) A project team gathered information necessary to consolidate 'Global Tea' and 'Organic Juice' companies. The
5. Project Network Design (5 pts.) (Follow Topic: Project Network) A project team gathered information necessary to consolidate 'Global Tea' and 'Organic Juice' companies. The result of their consolidation data collection effort is shown in the table below: i. Develop a network (may draw the network using computer or by hand & scan): ii. Identify the highest slack time on activity (if there any) in the network (1 pt.) iii. Find the critical path (using forward pass & backward pass calculation) (1 pt.) iv. Find the project duration from the critical path. (1.5 pt.)