Question: Project Network Design (5 pts.) (Follow Topic 6: Project Network)) A project team gathered information necessary to consolidate Global Tea and Organic Juice companies. The
- Project Network Design (5 pts.) (Follow Topic 6: Project Network))
A project team gathered information necessary to consolidate Global Tea and Organic Juice companies. The result of their consolidation data collection effort is shown in the table below:
| # | Activity | Predecessor | Duration |
| 1 | Codify Accounts | None | 19 |
| 2 | File Articles of Unification | None | 30 |
| 3 | Unify price and credit policy | None | 72 |
| 4 | Unify personnel policies | None | 27 |
| 5 | Unify data processing | 1 | 29 |
| 6 | Train accounting staff | 1 | 7 |
| 7 | Pilot run data processing | 5 | 15 |
| 8 | Calculate P & IL and BS | 6,7 | 12 |
| 9 | Transfer real property | 2 | 27 |
| 10 | Train salesforce | 3 | 35 |
| 11 | Negotiate with unions | 4 | 55 |
| 12 | Determine capital needs | 8 | 20 |
| 13 | Explain personnel policies | 11 | 23 |
| 14 | Secure line of credit | 9,12 | 16 |
| 15 | End | 10,13,14 | 0 |
- Develop a network (you may draw the network using computer or by hand & scan): (2 pts.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts