Question: 5. The basic activities, with their elapsed times (in working weeks), required to construct a habitable frame house are listed in the table: Arrange the
5. The basic activities, with their elapsed times (in working weeks), required to construct a habitable frame house are listed in the table: Arrange the work activities according to precedence requirements and draw the arrow diagram. Calculate the early and late start dates.
a. What is the earliest completion time?
b. What is the Critical path?