Question: 5. The basic activities, with their elapsed times (in working weeks), required to construct a habitable frame house are listed in the table: Arrange the

5. The basic activities, with their elapsed times (in working weeks), required to construct a habitable frame house are listed in the table: Arrange the work activities according to precedence requirements and draw the arrow diagram. Calculate the early and late start dates.

a. What is the earliest completion time?

b. What is the Critical path?

5. The basic activities, with their elapsed times

\begin{tabular}{|l|l|l|l|} \hline Activity & Feeks & Fetivity & Weeks \\ \hline Clear site & 2 & Finish plumbing & 4 \\ \hline Exeavate basement & 3 & Interior painting & 6 \\ \hline Rough walls \& floors & 9 & Wallboard & 8 \\ \hline Exterior siding & 7 & Exterior fixtures & 2 \\ \hline Pour basement & 6 & Exterior paint & 6 \\ \hline Roof Frames & 4 & Finish flooring & 5 \\ \hline Rough in plumbing & 9 & Roofing & 4 \\ \hline Electrical & 8 & Landscaping & 6 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!