Question: 5. The ______________ is the longest path in the network from start to finish. first-order path final-order path complex-grade path none of the above 6.
5. The ______________ is the longest path in the network from start to finish.
| first-order path | ||
| final-order path | ||
| complex-grade path | ||
| none of the above |
6. In the Critical Path Method, Crash time is __________.
| planned activity duration for additional cost | ||
| minimum activity duration for additional cost | ||
| maximum activity duration for additional cost | ||
| none of the above |
7. Project planning is usually a function of the following personnel __________
| top manager, middle managers and cross-functional team | ||
| top and middle managers | ||
| middle managers and cross-functional team | ||
| none of the above |
8. Constant-time networks represent the __________ case.
| easiest | ||
| simplest | ||
| hardest | ||
| none of the above |