Question: 5) Using the information given in the following table: (A) Identify the critical path. (10 points) (B) Determine expected project duration. (5 points) begin{tabular}{lll} Activity
5) Using the information given in the following table: (A) Identify the critical path. (10 points) (B) Determine expected project duration. (5 points)

\begin{tabular}{lll} Activity & Precedes & Duration \\ \hline Start & a, b, c & - \\ a & d & 5 \\ d & f & 6 \\ f & g & 2 \\ b & e & 5 \\ e & f & 9 \\ c & h & 4 \\ h & g,i & 6 \\ g & end & 3 \\ I & end & 1 \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts