Question: 50. Whenever a customer requests changes, the project manager should Select one: a. have the appropriate project team members estimate the effects on the project

50. Whenever a customer requests changes, the project manager should

Select one:

a. have the appropriate project team members estimate the effects on the project cost and schedule.

b. stop the project's progress.

c. do a quick estimate and say if the change is ok or not.

d. ignore the request and deliver the product promised.

9.

Effective project management requires a ____ leadership style.

Select one:

a. directive and participative

b. hierarchical and directive

c. participative and consultative

d. autocratic and consultative

14.

____ is the creative step in the problem-solving process.

Select one:

a. Evaluate the alternative solutions

b. Implement the solution

c. Identify possible solutions

d. Revise the project plan

16.

____ is the initial stage of the team development process. It involves the transition from individual to team member.

Select one:

a. Storming

b. Norming

c. Performing

d. Forming

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!