Question: 5-3 During the most recent month at Luinstra Corporation queue time was 4.5 days, inspection time was 0.8 day, process time was 1.9 days, wait

 5-3 During the most recent month at Luinstra Corporation queue time
was 4.5 days, inspection time was 0.8 day, process time was 1.9

5-3 During the most recent month at Luinstra Corporation queue time was 4.5 days, inspection time was 0.8 day, process time was 1.9 days, wait time was 5.1 days and move time was 0.7 day. REQUIRED: a. Compute the throughput time b. Compute the manufacturing cycle efficiency(MCE)