Question: 56 mal Exam (75 Multiple Cholce) i An unanticipated event that occurs which is beneficial to a project is known as a(n) Multiple Choice Management
56

mal Exam (75 Multiple Cholce) i An unanticipated event that occurs which is beneficial to a project is known as a(n) Multiple Choice Management Reserve Success Factor Opportunity Risk Desirable event