Question: 56 Question 2: Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $600,000, what are
56 Question 2: Below is a project WBS with cost apportioned by percent. If the total project cost is estimated to be $600,000, what are the estimated costs for the following deliverables? Router systems project Cost: $600.000 Definition Design 409 10% Implementation 5096 Objectives 494 Requirements 89 In-house Testing 4098 Customer festing & review 10% Flas Inputs 398 Outputs 391 Interfaces 10% Programming 204 40
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
