Question: 5.You are the project manager for a large manufacturing project, which includes creating a microchip for the new cell phones your company is making for
5.You are the project manager for a large manufacturing project, which includes creating a microchip for the new cell phones your company is making for release in the coming month. Your sponsor is looking through the information in your risk register and notices that there is no any information about the probability of meeting your budget with the current reserves you have set aside. What mechanism(s) is(are) appropriate to identify the probability of meeting the current budget within the given reserve?
Step by Step Solution
3.49 Rating (159 Votes )
There are 3 Steps involved in it
The purpose of a risk register in project management is to record the details of all risks that have ... View full answer