Question: 6 0 . 0 % complete Question A project manager is leading a project that received a request for additional scope caused by changes in
complete
Question
A project manager is leading a project that received a request for additional scope caused by changes in market demand. The change request also seeks a more rapid delivery time frame.
Which two actions should the project manager take? Choose two
AAssess company performance and the scope of other projects to ensure minimal impact.
BOrganize a workshop with the sponsors and ask them to increase the project budget.
CCollect data and analyze the business environment to validate the business benefits.
DAssess new technologies and competitors, then benchmark the change against them.
EOrganize a risk workshop, then update the risk management plan and the risk register.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock