Question: 6 0 As a project coordinator for a project management company, you are planning to build a new library by col engineer. After researching, you

60
As a project coordinator for a project management company, you are planning to build a new library by col engineer. After researching, you determined that for a library covering a total area of 300 square feet, the cost is $3000. The current area for the library you are designing to build is 825 square feet. Using the Paran approximate total cost for building the library?
a. $29,250
b. $22,500
c. $24,750
d. $27,000
 60 As a project coordinator for a project management company, you