Question: 6 0 points ) Deferrable server. For the following set of implicit - deadline periodic tasks with a deferrable server ( TDS ) : Task

60 points) Deferrable server. For the following set of implicit-deadline periodic tasks with
a deferrable server (TDS):
Task (Ti) Period (pi ) Execution Time (ei )
T181
T261
T391
T DS 51
a) Assume Rate Monotonic method is employed, check the schedulability.
b) Assume the Earliest Deadline First is employed, check the schedulability.
If there are 3 aperiodic jobs:
released at 2,8 and 12
exec time 2,1 and 2
c) Construct a preemptive Rate Monotonic schedule and present your schedule using a
Gantt chart (24 unit of time).