Question: 6) (10 pts) Given the following data, calculate the projected available balance, the planned MPS receipts and ATP values. The lot size is 200. The

6) (10 pts) Given the following data, calculate

6) (10 pts) Given the following data, calculate the projected available balance, the planned MPS receipts and ATP values. The lot size is 200. The time fence is 2 weeks. On hand inventory is 80 units. Period Forecast Customer Orders Projected on Balance 1 2 3 4 5 | 150 | 150 | 150 | 150 | 150 90 80 75 95 100 6 150 120 ATP