Question: 6 . [ 3 0 points ] Consider following project. Activity Activity Time ( weeks ) Immediate Predecessor Number of workers reqd. A 4 2
points Consider following project. Activity Activity Time weeks Immediate Predecessor Number of workers reqd. A B C D B C E A F D a Draw a project network. If you draw on a paper, scan it and insert it to the document with answers, Images submitted separately will not be graded. b Develop resource requirement plan similar to figure See presentation slide for an example. c Assume that each task can be performed independently of the other tasks. No predecessor relationships Now, do a resource leveling. How many workers are required? What is the project completion time? Show all work to earn credit. d Assume that each task can be performed independently of the other tasks. But now, you have only workers available at any given time. Perform resourcelimited scheduling. What is the new completion time for the project? Show all work to earn credit.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock