Question: For the following Project: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Crash Cost Immediate Predecessor A 4 3 $2,000 $2,100 - B 2

For the following Project:

Activity

Normal Time (weeks)

Crash Time

(weeks)

Normal Cost

Crash Cost

Immediate Predecessor

A

4

3

$2,000

$2,100

-

B

2

1

$2,200

$2,800

-

C

3

3

$500

$500

-

D

8

6

$2,300

$2,600

A

E

6

3

$900

$1,200

B

F

3

2

$3,000

$4,200

C

G

4

2

$1,200

$2,000

E, F

How long will the project take?

What is the total cost to complete the project in normal time?

If the project is to be shortened by 1-week, which activity will be reduced and how much will the cost be increased?

What is the maximum time that the project can be crashed? How much will the cost increase if it is crashed the maximum?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!