Question: For the following Project: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Crash Cost Immediate Predecessor A 4 3 $2,000 $2,100 - B 2
For the following Project:
| Activity | Normal Time (weeks) | Crash Time (weeks) | Normal Cost | Crash Cost | Immediate Predecessor |
| A | 4 | 3 | $2,000 | $2,100 | - |
| B | 2 | 1 | $2,200 | $2,800 | - |
| C | 3 | 3 | $500 | $500 | - |
| D | 8 | 6 | $2,300 | $2,600 | A |
| E | 6 | 3 | $900 | $1,200 | B |
| F | 3 | 2 | $3,000 | $4,200 | C |
| G | 4 | 2 | $1,200 | $2,000 | E, F |
How long will the project take?
What is the total cost to complete the project in normal time?
If the project is to be shortened by 1-week, which activity will be reduced and how much will the cost be increased?
What is the maximum time that the project can be crashed? How much will the cost increase if it is crashed the maximum?