Question: 6 . A method has been engineered and a time study was completed on it . The method has produced an average overall time of

6. A method has been engineered and a time study was completed on it. The method has produced an average overall time of 2.32 minutes. The overall pace rating applied to the job was 125%. The company has PF&D allowances of 15%.
a. Determine rated time/normal minutes, the total allowed time/standard minutes, the standard hour rate for the job per 100 units, and pieces per hour.
b. The labor rate per hours is $15.30 per hour. What is the labor cost per unit?