Question: 6 An engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment

6 An engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The pumper can pump 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is a 25 rental option that will cost $19,000 per year. In addition, an extra $13.5 per hour labor cost will be incurred for operating the rented points equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 65 days per year? The MARR is 11% per year. Skipped The annual worth of plan 1 lease optimistic is $ eBook The annual worth of plan 1 most likely is $ The annual worth of plan 1 pessimistic is $ Hint The annual worth of plan 2 rental is $ Plan 1 lease optimistic is (Click to select) v than rental of plan 2. Ask Plan 1 most likely is (Click to select) |than rental of plan 2 References Plan 1 lease pessimistic is (Click to select) |than rental of plan 2
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
