Question: 6. Following table provides tasks on an assembly line, task times, and their immediate predecessors. + Task Time (Minutes) Immed. Pred. A 0.2 None B

6. Following table provides tasks on an assembly

6. Following table provides tasks on an assembly line, task times, and their immediate predecessors. + Task Time (Minutes) Immed. Pred. A 0.2 None B 0.4 None B C 0.3 None D 1.0 BC E 0.2 F 0.8 DE 0.2 D 1.0 F G The cycle time (time between each unit coming out) is 1.3 minutes. Draw the precedence diagram. Balance the line (assign all tasks) using the longest task time rule. Calculate the efficiency. Work station Eligible Task Task time Sum Task Idle time time

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!