Question: 6. On the calendar a project activity estimated to require 24 person days to complete is shown to start on Wednesday (at the start of

6. On the calendar a project activity estimated

6. On the calendar a project activity estimated to require 24 person days to complete is shown to start on Wednesday (at the start of the day) and is last worked on Friday of the following week with no work occurring on weekends. How many workers were assigned to this activity