6. Product A is assembled from two units of S1 and three units of S2. S1 is made of one unit of C1, four units of C2 and one unit of C3. S2 is made of three units of C2 and two units of C3.
- Draw a tree structured BOM for product A.
- How many C3s are needed to fill an order for 100A's?
- Assume no inventory on hand, products take one day to assemble, subassemblies take two days and components take three days to order. When should an order be released for C3 if 100A's are needed by day 7.