Question: 6 . These are the tasks necessary for the final assembly of a hospital bed, the time needed to perform each task, and the operations

6. These are the tasks necessary for the final assembly of a hospital bed, the time needed to perform each task, and the operations that must be completed prior to subsequent operations. The time available is 00 minutes per day, and the required output rate is 25 beds per day.
Time (min) Immediate Predecessors
Task
A
4
None
B
5
None
C
8
None
D
4
A
LL
E
3
A,B
F
3
B
G
5
D,E
H
7
F
1
1
G,H
#bA
J
7
K
4
C,J