Question: The following table lists the tasks necessary for final assembly of a hospital bed, along with precedence relationships and times needed to perform each task.
The following table lists the tasks necessary for final assembly of a hospital bed, along with precedence relationships and times needed to perform each task. Construct a precedence diagram and balance the assembly line for a desired cycle time of 14 minutes. Draw a schematic diagram of your balanced line. How many beds can be assembled in an 8 hour period?
| Element | Precedence | Time (min) |
| A | None | 4 |
| B | None | 5 |
| C | None | 8 |
| D | A | 4 |
| E | A, B | 3 |
| F | B | 3 |
| G | D, E | 5 |
| H | F | 7 |
| I | G, H | 1 |
| J | I | 7 |
| K | C, J | 4 |