Question: 6 . What is a dummy activity? 7 . Consider Figure 5 - 1 4 . Paths a - b - c and a -

6. What is a dummy activity?
7. Consider Figure 5-14. Paths a-b-c and a-b-d converge at activity f, but we ignored this
potential merge problem in the text. Why?
8. What is meant by project slack?
9. When using AON networks, how does one indicate an event such as a project milestone?
10. A probabilistic network has a critical path of 21 days and a 0.95 probability of completing
this path in 24 days. Therefore, the project has 0.95 chance of being finished by the end of
the 24th day. True or False? Briefly explain your answer.