Question: 61.Setting a work resources maximum units value to 200% implies all of the following EXCEPT: A.That work resource's calendar has decreased the non-working days and

61.Setting a work resources maximum units value to 200% implies all of the following EXCEPT:

A.That work resource's calendar has decreased the non-working days and hours to accommodate for 200% capacity

B.There is one resource working "double" time on the project

C.There are two 100% resources available for the project

D.There are four 50% resources available for the project

62.Cost resources have their own resource calendar for setting non-working time.

TRUE

FALSE

63. Regarding Material Resources, the term "consumables" means the resources are used up (the quantity of the material is depleted) as the project proceeds.

TRUE

FALSE

64. The Maximum Units Value is the maximum capacity of a resource to accomplish tasks during the calendar schedule for that resource.

TRUE

FALSE

65. Setting a work resources maximum units value to a certain limit prevents the project manager from accidentally scheduling that resource when they are not available.

TRUE

FALSE

66. Resource leveling is one way of resolving an overallocation manually.

TRUE

FALSE

67. Overallocation is a serious problem in project management that should be avoided at all costs.

TRUE

FALSE

68. All of the following are ways to resolve resource overallocations EXCEPT:

A.Replace the overallocated resource with another resource

B.Manually editing an assigment of resource to task

C.Assign an additional resource to the task so that both resources share the work

D.Reduce the duration of the task in the Assignment Information or Assign Resources dialog box

69.WHICH of the following terms describes when the resource's assignments exceed the resource's maximum capacity for any period of time?

A.Underallocated

B.Resource allocations

C.Fully allocated

D.Overallocated

70.It is every project manager's objective/imperative to fully allocate all resources at all times throughout the project.

TRUE

FALSE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!