Question: 6.Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.Single choice. (1 Point) Risk breakdown structures Contingency
6.Organizations use __________ in conjunction with work breakdown structures to help management teams identify and eventually analyze risk.Single choice.
(1 Point)
Risk breakdown structures
Contingency breakdown structures
Scenario analysis
Organizational breakdown structure
7.An uncertain event or condition that, if it occurs, has a positive or negative effect on project objectives is termed aSingle choice.
(1 Point)
Random Chance
Disaster
Risk
Hazard
8.Purchasing an accident insurance policy would be an example of responding to risk by _____________ it.Single choice.
(1 Point)
Mitigating
Retaining
Ignoring
Transferring
9.This response is used when an identified Opportunity is not actively pursued.Single choice.
(1 Point)
Exploit
Share
Enhance
Accept
10.Adopting proven technology instead of experimental technology in order to eliminate technical failure would be an example of which risk response?Single choice.
(1 Point)
Mitigating
Retaining
Ignoring
Avoiding