Question: 7 0 . As a project manager, you are involved in purchasing various items for the project. However, you suddenly receive an official letter from
As a project manager, you are involved in purchasing various items for the project.
However, you suddenly receive an official letter from your client ordering the immediate
termination of the project. What will be your best course of action?
A Refer to Project Closure Guidelines in Organizational Process Assets
B Release the Project Team
C Perform Inspections & Audits
D Perform Procurement Audits