9. The following six activities constitute an overall bar chart portrayal of a fourmonth project.
Two months after the start of construction, Activities A, C, D, half of E, and onefourth of B were completed, for a cost of $10,500. Evaluate the status of the project. Using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead of or behind schedule.