Question: 7 / 8 83.4% PART 2 / CRITICAL PATH METHOD Ex. 6 Build a network of activities and calculate EST/EFR and LST/LFT and Total Float.

7 / 8 83.4% PART 2 / CRITICAL PATH METHOD Ex. 6 Build a network of activities and calculate EST/EFR and LST/LFT and Total Float. Activity 1-2 1-3 1-4 2-4 2-5 3-4 3-5 4-5 5-6 Duration 7 6 6 15 0 7 8 9