Question: QUESTION 2 The earliest start time and latest start time of activity C are, respectively, 0, 0 9, 9 9, 11 10, 12 None of


QUESTION 2
-
The earliest start time and latest start time of activity C are, respectively,
0, 0
9, 9
9, 11
10, 12
None of the above
QUESTION 3
-
The latest start time and latest finish time of activity F are, respectively,
0, 0
9, 9
9, 11
10, 12
None of the above
QUESTION 4
-
The earliest finish time and latest finish time of activity G are, respectively,
0, 0
9, 9
9, 11
10, 12
None of the above
QUESTION 5
-
The earliest start time and latest start time of activity H are, respectively,
0, 0
9, 9
9, 11
10, 12
None of the above
QUESTION 6
-
The earliest start time and earliest finish time of activity F are, respectively,
0, 0
9, 9
9, 11
10, 12
None of the above
QUESTION 7
-
The slack time of activity D is
0
1
2
3
None of the above
QUESTION 8
-
The slack time of activity F is,
0
1
2
3
None of the above
QUESTION 9
-
The activities on the critical path are
C, D, G, H, I.
C, D, E, F, I.
A, B, G, H, I.
A, B, E, F, I.
None of the above.
QUESTION 10
-
The total time in weeks needed to finish the project is
12
13
14
24
None of the above