Question: QUESTION 2 The earliest start time and latest start time of activity C are, respectively, 0, 0 9, 9 9, 11 10, 12 None of

QUESTION 2 The earliest start time and latest

QUESTION 2 The earliest start time and latest

QUESTION 2

  1. The earliest start time and latest start time of activity C are, respectively,

    0, 0

    9, 9

    9, 11

    10, 12

    None of the above

QUESTION 3

  1. The latest start time and latest finish time of activity F are, respectively,

    0, 0

    9, 9

    9, 11

    10, 12

    None of the above

QUESTION 4

  1. The earliest finish time and latest finish time of activity G are, respectively,

    0, 0

    9, 9

    9, 11

    10, 12

    None of the above

QUESTION 5

  1. The earliest start time and latest start time of activity H are, respectively,

    0, 0

    9, 9

    9, 11

    10, 12

    None of the above

QUESTION 6

  1. The earliest start time and earliest finish time of activity F are, respectively,

    0, 0

    9, 9

    9, 11

    10, 12

    None of the above

QUESTION 7

  1. The slack time of activity D is

    0

    1

    2

    3

    None of the above

QUESTION 8

  1. The slack time of activity F is,

    0

    1

    2

    3

    None of the above

QUESTION 9

  1. The activities on the critical path are

    C, D, G, H, I.

    C, D, E, F, I.

    A, B, G, H, I.

    A, B, E, F, I.

    None of the above.

QUESTION 10

  1. The total time in weeks needed to finish the project is

    12

    13

    14

    24

    None of the above

Doug Casey is in charge of planning and coordinating next quarter's sales management training program for his company. Doug listed the following activity information for this project. Activity Description Immediate Predecessor(s) Estimated Time (weeks) A . B D 3 3 3 4 E Plan topic Invite speakers List meeting locations Select location Finalize speaker travel plans Make final check with speakers Prepare and mail brochure Take reservations Handle last minute details 2 F 2 B,D E B,D G F, H 2 G H 1 3 2 Before answering the following questions, you may want to schedule the project by determining the earliest start time, earliest finish time, latest start time, and latest finish time for each activity, and to compute the slack time for each activity. You may use the following table: Activity Immediate Estimated Time Earliest Earliest Latest Latest Slack Predecessor(s) (weeks) Start Finish Start Finish A 3 3 B A 3 C D E F G BD E B, D G FH 4 2 2 2 H 3 I 2 QUESTION 1 Which of the following network is a good representation of the predecessor relationships of the activities? A 3 B E Start Finish G D 4 3 3 A B E F 2 Start Finish C 3 H 3 4 2 A B F E 2 w Start Finish D 4 G 2 H 3 3 B A 3 E B 3 Start Finish 2 D 4 G 2 H 3 None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!