Question: 7 . - 9 . Donuts for July 4 th ( You have 2 attempts for this problem ) 3 points possible ( graded )
Donuts for July th You have attempts for this problem
points possible graded
Dunking Donuts in New York's Times Square is preparing its shops for July th Independence Day. They are introducing a special July th Donut with a red, white and blue cream inside is that a good marketing idea??
The average and variability of the amount of cream of all produced donuts should be very consistent, and, as the colorcream process is new to the company Xbar and Rcharts are set up to control the process. The following data was collected during June to prepare for the production for the July th weekend. The target is g
We assume for this practice problem that these samples are sufficient for calculating the control limits although are recommended.
From this data, you can calculate the following values:
Xbarbar: g
Rbar: g
Table of Control Chart Constants
What are the upper control limit UCL center line CL and lower control limit LCL for Xbar?
UCLXbar; CLXbar; LCLXbar
UCLXbar; CLXbar; LCLXbar
UCLXbar; CLXbar; LCLXbar
UCLXbar; CLXbar; LCLXbar
unanswered
What are the upper control limit UCL center line CL and lower control limit LCL for R
UCLR; CLR; LCLR
UCLR; CLR; LCLR
UCLR; CLR; LCLR
UCLR; CLR; LCLR
unanswered
What can you conclude from this data?
The production line data indicates an outofcontrol sample. An assignable cause should be identified and eliminated.
The production line data is all in control, but the amount of cream should be increased by g
The production line is all in control, no further work needed
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock