Question: [7] b) A project has the precedence relationship and activity time given in Table Q 6(b). With the help of a network diagram identify the

[7] b) A project has the precedence relationship

[7] b) A project has the precedence relationship and activity time given in Table Q 6(b). With the help of a network diagram identify the followings: i. Slack time for each activity. ii. The activities that are on critical path. iii. The project completion time. Table Q 6(b) Activity Activity time (Days) Immediate Predecessor (s) A 2 B 5 4 D 4 E 8 A F 3 B, C, D G 4 E, F H 7 F I 3 G J 3 G K 3 H