Question: Problem #1: Refer to the project described below. Construct an AOA network for this project. (2 pts) Activity A B C D E F G
Problem #1: Refer to the project described below. Construct an AOA network for this project. (2 pts)
| Activity | A | B | C | D | E | F | G | H | I | J | K | L |
| Predecessor | - | - | - | A | C | A | B,D,E | C | H | F,G,I | H | J,K |
| Duration (weeks) | 3 | 2 | 4 | 5 | 2 | 1 | 3 | 2 | 3 | 4 | 2 | 3 |
Problem #2: Refer to the project described below. Construct an AOA network for this project. (2 pts)
| Activity | A | B | C | D | E | F | G | H | I |
| Predecessor | - | - | A | A | B, D | A, E | C, F | A, E | G,H |
| Duration (weeks) | 3 | 2 | 4 | 5 | 2 | 1 | 3 | 2 | 3 |
Problem #3: A project involving the development of a communication module at a telecommunication company consists of totally 13 activities. The immediate predecessors and activity time (in weeks) are shown below. Complete the network diagram and answer the 4 multiple-choice questions. (6 pts)
| Activity | Predecessor | Time duration (in weeks) | te = ? | slack | ||
| to | tm | tp | ||||
| A | -- | 2 | 3 | 4 |
|
|
| B | A | 3 | 4 | 11 |
|
|
| C | A | 2 | 3 | 4 |
|
|
| D | A | 3 | 5 | 7 |
|
|
| E | C | 4 | 5 | 6 |
|
|
| F | C | 2 | 3 | 4 |
|
|
| G | C, D | 4 | 5 | 12 |
|
|
| H | C, D | 2 | 3 | 10 |
|
|
| I | B, E | 3 | 4 | 5 |
|
|
| J | F, G | 7 | 8 | 9 |
|
|
| K | H | 2 | 3 | 4 |
|
|
| L | J, K | 3 | 4 | 5 |
|
|
| M | I, L | 1 | 8 | 9 |
|
|
- What is the Total Project completion Time?
- Identify the Critical Path (list of activities).
- Calculate the slack for each activity and fill in the table.