Question: 7) Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. (a)Draw the precedence diagram for the set of
7) Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. (a)Draw the precedence diagram for the set of tasks. (b) Calculate the theoretical minimum number of workstations. (c) Balance this line using the ranked positional weight heuristic. (d) How much idle time is there, summed over all workstations? (e) What is the efficiency of this line
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
