Question: Q2 Precedence Diagram Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. (a) Draw the precedence diagram for

Q2 Precedence Diagram Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. (a) Draw the precedence diagram for the set of tasks. (b) Calculate the theoretical minimum number of workstations. (c) Balance this line using the largest candidate rule. (d) What tasks are assigned to which stations? (e) Does the solution have the minimum number of stations? Explain. (f) How much idle time is there, summed over all workstations? (g) What is the efficiency of this line