Question: 7. Draw a task network where: a) tasks B and C are successors to A b) Tasks D and E are successors to B c)
7. Draw a task network where:
a) tasks B and C are successors to A
b) Tasks D and E are successors to B
c) Task F is a successor to C
d) Task G is a successor to E and F
e) Task H is a successor to D and G
8. Using your drawing from question 7, calculate the early time (EFT) of Task H using the below durations:
Task A=3 Task B=5 Task C=8 Task D=2 Task E=4 Task F=9 Task G=6 Task H=4
What is the project EFT?
9. What is the critical path for the Task network defined by the above questions?
10. If Task Es duration increases to 8 days.
a) What is the new duration and?
b) What is the new critical path?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
