Question: A contractor has developed the tasks, durations, and predecessor relationships in the following table for part of a new building. The Beta distribution is assumed

A contractor has developed the tasks, durations, and predecessor relationships in the following table for part of a new building. The Beta distribution is assumed for all activity times.
Task Immediate Predecessor(s) Time Estimates (In Weeks)
Optimistic Most Likely Pessimistic
A None 5619
B A 567
C A 345
D B 135
E B 3417
F C 246
G D 345
H E, F 234
7. Draw the precedence network for the project. You may use the shape tools in Word or PowerPoint, or the drawing application of your choice, and insert (copy & paste) the diagram into the Word file. What are the ES/EF (earliest start/finish) and the LS/LF (latest start/finish) for each task based on the expected task times? Write these times on the network diagram. Hint: It may be helpful to create dummy start and/or end tasks with task times of 0 to tie the ends of the network together. (10 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!