Question: A contractor has developed the tasks, durations, and predecessor relationships in the following table for part of a new building. The Beta distribution is assumed
A contractor has developed the tasks, durations, and predecessor relationships in the following table for part of a new building. The Beta distribution is assumed for all activity times.
Task Immediate Predecessors Time Estimates In Weeks
Optimistic Most Likely Pessimistic
A None
B A
C A
D B
E B
F C
G D
H E F
Draw the precedence network for the project. You may use the shape tools in Word or PowerPoint, or the drawing application of your choice, and insert copy & paste the diagram into the Word file. What are the ESEF earliest startfinish and the LSLF latest startfinish for each task based on the expected task times? Write these times on the network diagram. Hint: It may be helpful to create dummy start andor end tasks with task times of to tie the ends of the network together. pts
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock