Question: 7- For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Activity Duration IPA ES

7- For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table.

Activity

Duration

IPA

ES

EF

LS

LF

TF

FF

A

3

B

5

C

6

A

D

9

A, B

E

4

A, B

F

6

B

G

5

C, D

H

12

D, E

I

7

D, E, F

J

9

E

K

10

G, H, I

L

6

I, J

M

4

G, I

N

2

K