Question: - For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Activity Duration IPA ES
- For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table.
| Activity | Duration | IPA | ES | EF | LS | LF | TF | FF |
| A | 5 | |||||||
| B | 7 | A | ||||||
| C | 10 | A | ||||||
| D | 5 | A | ||||||
| E | 9 | A | ||||||
| F | 6 | B | ||||||
| G | 4 | B, C | ||||||
| H | 8 | B, C, D | ||||||
| I | 2 | C, D | ||||||
| J | 5 | E | ||||||
| K | 8 | F | ||||||
| L | 9 | E, G | ||||||
| M | 7 | F, G, H | ||||||
| N | 3 | F, G, H, I | ||||||
| O | 6 | H, I | ||||||
| P | 4 | M, N, O | ||||||
| Q | 3 | K, L | ||||||
| R | 5 | L, M | ||||||
| S | 4 | J, P | ||||||
| T | 6 | Q | ||||||
| U | 4 | Q, R | ||||||
| V | 1 | T, U, S |