Question: - For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table. Activity Duration IPA ES

- For the following schedule, draw the node network, perform the CPM calculations, mark the critical path, and complete the table.

Activity

Duration

IPA

ES

EF

LS

LF

TF

FF

A

5

B

7

A

C

10

A

D

5

A

E

9

A

F

6

B

G

4

B, C

H

8

B, C, D

I

2

C, D

J

5

E

K

8

F

L

9

E, G

M

7

F, G, H

N

3

F, G, H, I

O

6

H, I

P

4

M, N, O

Q

3

K, L

R

5

L, M

S

4

J, P

T

6

Q

U

4

Q, R

V

1

T, U, S

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!