Question: 7. On a project network, the activity times are derived from the A. Organization breakdown structure. B. Work packages. C. Budget. D. Project proposal. 8.

7. On a project network, the activity times are derived from the A. Organization breakdown structure. B. Work packages. C. Budget. D. Project proposal. 8. The cost impact of a risk event occurring as a project proceeds through its life cycle E. Responsibility matrix. tends to A. Slowly rise. B. Drop sharply and then level out. C. Rise sharply and then level out. D. Remain about the same. E. Slowly drop