Question: On a project network, the activity times are derived from the Question 1 options: responsibility matrix. project proposal. budget. work packages. Question 2 ( 1
On a project network, the activity times are derived from the
Question options:
responsibility matrix.
project proposal.
budget.
work packages.
Question point
An activity that has more than one dependency arrow flowing into it is termed an
Question options:
parallel activity.
critical path.
independent activity.
burst activity.
merge activity.
Question point
The critical path in a project network is the
Question options:
network path with the most difficult activities.
network path using the most resources.
longest path through the network.
shortest path through the network.
Question point
Activities which can take place at the same time are termed
Question options:
burst activity.
parallel activity.
independent activity.
critical path
merge activity.
Question point
Which of the following is NOT one of the basic rules to follow when developing project networks?
Question options:
An activity identification number must be larger than that of any preceding activities.
An activity cannot begin until all preceding activities have been completed.
Conditional statements are allowed but looping statements are not allowed.
Each activity must have a unique identification number.
Networks flow from left to right.
Question point
The preferred method for situations involving strategic decision making, projects with a high degree of uncertainty, and projects with an unstable scope is the approach to estimating project time and costs.
Question options:
bottomup
reference class
experiential
professional estimation
topdown
Question point
The salary of the project manager and temporary rental space for the project team would be classified as costs.
Question options:
fixed
direct
general and administrative overhead
interaction
direct project overhead
Question point
The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
Question options:
rise at first, but then begin to decline over the life of the project.
decline over the life of the project.
decline at first, but then begin to rise over the life of the project.
remain the same over the life of the project.
rise over the life of the project.
Question point
is a measure of how easy it would be to notice that a risk event was going to occur in time to take mitigating action, that is how much warning you would have.
Question options:
Detection difficulty
Impact scaling
Warning assessment
Probability analysis
Awareness level
Question point
Risks are evaluated in terms of
Question options:
likelihood and impact.
likelihood and cost.
time and impact.
impact and cost.
cost and schedule.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock