Question: 7.) The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is
7.) The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $25, the overhead rate is 1.0 times laor cost, and material cost is $5 per customer.
| Unit | Employees | Customers Processed/Day | |
| A | 4 | 36 | |
| B | 5 | 40 | |
| C | 8 | 60 | |
| D | 3 | 20 |
a.) Compute the labor productivity and the multifactor productivity for each unit. Use an eight-hour day for multifactor productivity.