Question: 7) What is the slack time for Activity A? Activity Expected Activity Time ES EF LS LF Slack A 8 0 8 0 8 B

7) What is the slack time for Activity A?

Activity Expected Activity Time ES EF LS LF Slack
A 8 0 8 0 8
B 4 0 4 6 10
C 6 8 14 10 16
D 11 8 19 8 19
E 9 4 13 10 19
F 3 14 16 16 19
G 1 19 19 19 20