Question: 71)Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which of the following will

71)Halfway through a project, the project manager is told it needs to be completed four weeks earlier than originally planned. Which of the following will MOST likely be impacted to accomplish this goal?

A. Risks B. Budget C. Quality

D. Deliverables