Question: 7-4. Use the three times given compute the expected time of completion AND the standard deviation for each activity. Use Excel. TIME IN DAYS ACTIVITY
7-4. Use the three times given compute the expected time of completion AND the standard deviation for each activity. Use Excel. TIME IN DAYS
| ACTIVITY | OPTIMISTIC | MOST LIKELY | PESSIMISTIC |
| A | 5 | 6 | 7 |
| B | 8 | 8 | 11 |
| C | 6 | 8 | 11 |
| D | 9 | 12 | 15 |
| E | 5 | 6 | 9 |
| F | 5 | 6 | 7 |
| G | 2 | 3 | 7 |
| H | 4 | 4 | 5 |
| I | 5 | 7 | 8 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts