Question: Question #1 Listed in the below table are the tasks and times for a capstone project. Activity Predecessor activities Optimistic time, days Most likely time,
Question #1
Listed in the below table are the tasks and times for a capstone project.
| Activity | Predecessor activities | Optimistic time, days | Most likely time, days | Pessimistic time, days |
| A | - | 2 | 3 | 4 |
| B | A | 8 | 9 | 10 |
| C | A | 7 | 9 | 11 |
| D | B | 7 | 9 | 10 |
| E | C | 8 | 9 | 11 |
| F | D, E | 2.5 | 3 | 3.5 |
This projects critical path, expected time of completion in days, and variance of expected time in days, respectively, are:
a ) A-C-E-F, 24162416, 2.5
b) A-B-E-F, 24162416, 2.5
c) A-B-D-F, 23562356, 2.5
d) A-C-D-F, 23562356, 2.5
Q2) The O, M, and P times, in days, for the tasks of a project along its critical path are: 10-12-14, 12-21-36, 12-15-18, and 2-6-10. Similar times along a sub-critical path are: 2-9-10,12-15-24, and 12-18-24. By fast-tracking, the expected times of the tasks along the critical path were reduced by a total of 14 days. The expected time, in days, of project completion is:
a) 55
b) 41
c) 42
d) 43
Q3) A senior capstone project begins with the task of forming the team, whose times are O = 1 day, M = 2 days, P = 3 days. Next task of requirement analysis has O = 2 days, M = 3 days, P = 5 days. Subsequent two tasks are parallel: designing solution alternatives (whose times are: O = 5 days, M = 7 days, P = 9 days) and applying project management techniques (whose times are: O = 2 days, M = 3 days, P = 3.5 days). The subsequent task is selecting and building a solution (whose times are: O = 12 days, M = 14 days, P = 17 days). The final task is testing the solution, data gathering, and preparing the final report (whose times are: O = 3 days, M = 4 days, P = 5 days). The expected time of completing the capstone project and the standard deviation in the expected time, respectively in days, are:
1) 26/14, 1.633
b) 301/3, 1.633
c) 331/4, 1.633
4) 261/4, 2.668
Please answer it as soon as possible I don't have time I request you for solution and correct answers