Question: 8 (1 point) is a method for developing the shortest schedule when the quantity of resources is fixed. It will extend the project completion time

8 (1 point) is a method for developing the shortest schedule when the quantity of resources is fixed. It will extend the project completion time if necessary. a Resource leveling b Resource constraint c Resource-limited scheduling d Resource Planning