Listed below are selected line items from the Cost of Quality Report for Royce Manufacturing for last month.
Training employees: $1,200
Inspection of products: $1,000
Scrap due to defects: $800
Warranty claims: $500
Quality audits: $700
What is Royce Manufacturing's total prevention and appraisal cost for last month?
$1,700
$2,200
$2,900
$3,400