Question: 8 10 A os The Cyclon project team has started gathering the information necessary to develop a project network predecessor activities and activity time in
8 10 A os The Cyclon project team has started gathering the information necessary to develop a project network predecessor activities and activity time in days. The results of their meeting are found in the following table Activity Description Duration Predecessor Design Procure prototype parts A Fabricate parts 8 A D Assemble prototype 5 B, C Laboratory test D Field test Adjust design H Order stock components Order custom components 12 0 Assemble test production unit 9 Test unit H, I 10 Document results Pro F 0 12 10 1e 9 E 6 1 1 X 3 Port A Draw the project network Compute the early, late, and sack times for each activity What is the ES for Activity ? Part A. Draw the project network. Compute the early, late, and slack times for each activity. What is the ES for Activity D? What is the LF for Activity H? What is the slack for Activity C? What is the slack for Activity H? What is the slack for Activity 1? What is the length of the project? What is the critical path? time periods. A, C, D, E, F, G, I, J, KL Part C. Management is not happy with the schedule and wants the project completed as soon as possible. Unfortunately, they are not willing to approve additional resources. One team member pointed out that the network contained only finish-to-start relationships and that it might be possible to reduce project duration by creating start-to-start lags. After much deliberation the team concluded that the following relationships could be converted into start-to-start lags: Procure prototype parts could start 6 days after the start of Design, Fabricate parts could start 9 days after the start of Design Laboratory test could begin 1 day(s) after the start of Assemble prototype Feld test could start 6 days after the start of Laboratory test Adjust design could begin 7 days after the start of Field test Order stock and Order custom components could begin 5 days and 5 days, respectively, after Adjust design Test unit could begin 9 days after the start of Assemble test production unit Document results could start 3 days after the start of Test unit Reconfigure the Cycion schedule by entering all nine start-to-start Tags Reconfigure the Cyclon schedule by entering all nine start-to-start lags. w What is the ES for Activity D? What is the LF for Activity H? What is the slack for Activity C? What is the slack for Activity H? What is the slack for Activity 1? What is the length of the project? What is the critical path? 0 time periods. (A, C, D, E, F, G, I, J, K, L